What is the G99 Fast Track Process?
The G99 Fast Track process can help you connect your small generation or storage faster than a formal application.
Small Generation Installation 1:
• The basic design capacity is 32A (7.36kW) or less
AND
• The registered capacity is not more than 16A (3.68kW)
AND
• The total registered capacity is not more than 16A (3.68kW)
• An EREC G100 Export Limitation Scheme is not required as the manufacturer’s export limit is factory-set via the Inverter
Small Generation Installation 2:
• The basic design capacity be 32A (7.36kW) or less
AND
• The registered capacity is not more than 16A (3.68kW)
AND
• The total registered capacity is not more than 32A (7.36kW)
• An EREC G100 Export Limitation Scheme may be required, limiting export to the distribution network to no more than 16A (3.68kW)
Small Generation Installation 3:
• The basic design capacity must be 32A (7.36kW) or less (generating unit – inverter or battery)
AND
• The registered capacity is not more than 32A (7.36kW)
AND
• The total registered capacity is not more than 60A (14.72kW)
• An EREC G100 Export Limitation Scheme may be required, limiting export to the distribution network to no more than 32A (7.36kW)
You must also include Phase to Neutral Loop Impedance information using this form.
For extra support, click here.
Please note, you cannot connect until you receive confirmation that our assessment is complete. After this, the installer has up to 3 months to install and commission the generation. Once finished, they must submit Form A3-2 to the network operator within 28 days.
What next?
We aim to respond within 10 working days.

Frequently asked questions
Get in touch
Would you like to speak to us before you apply or have a question about an existing application?
Our team is available to help guide you through your generation journey. If you would like to speak to us we are here Monday to Friday 08:00 - 17:00.