Our multi-million pound launched in Spring 2023 and is now entering its final phase with the project set for completion in Summer 2025. This essential investment will boost the power supply to future-proof the electricity network for homes and businesses in the Alton and Bordon area of East Hampshire.
We’re investing £10.6million to boost Bordon’s electricity network.
Starting in May 2023, the Alton to Bordon investment project is installing 18km of cabling that will serve the needs of the area's 30,000 customers for many years to come.
The trenching works to install the cable ducts is ongoing and is scheduled to complete by November 2024. Once installed, the team will move to the next phase of the project to connect the ducts and pull the cable through. The cable pull is expected to complete by Summer 2025. Details of where and when these works will take place, will be available closer to the time.
Where are the team working?
Caker Lane - 28 September to 29 November: The team will remain in one place for works on Caker Lane, the team will be working on the stretch of Caker Lane that runs adjacent to Worldham Golf Club.
Caker Lane - Trenching works near the Oak Tree opposite the Three Horse Shoes Pub: 25 October to 14 November. These works take place under temporary traffic lights.
These works have been brought forward to avoid another road closure later down the line.
Farnham Road - 14th October to 10 November under a road closure.
Should you have any concerns about this, please do get in touch. The team will maintain access to businesses at all times.
Pedestrian access is maintained throughout. See our interactive map below for details on the full programme of work and to see where our team is working.
Where are the team going next?
Future works to pull the cable through and connect it to the electricity grid are currently being planned. The cable pull is expected to complete by Summer 2025 and details of the works will be published on this page soon.
All dates are subject to change and Hampshire County Council agreeing to these works.
For the rest of the programme, see our interactive map below.
Will the whole road be closed off?
No, we don’t close a road end to end. The road will be closed to through traffic, but local access will be maintained, in both directions, up to the section of road where the team is working.
To find the location of the team, visit our interactive map below.
A diversion route is provided
When we close a road, a temporary diversion route will be in place. The diversion route must be suitable for all diverted traffic and be of a similar grade of carriageway. Road signage will direct traffic to use the shortest available route, which meets these requirements.
There are other shorter routes available for cars and vans, which local road users may choose to use. However, these will not be signed in case HGVs follow the route.
Join us at our community events
As part of our commitment to keeping the local community informed, we have held six community drop-in events to date.
Traffic management
As we move into the final phase the project, our works will take place under temporary traffic lights for majority of the remaining construction programme. As the second phase will not require trenches in the road and will involve cable pulling and jointing, the necessity for road closures is vastly reduced.
Why we're boosting the electricity network
To meet future demand for electricity in the area and the uptake of low carbon technologies, the existing electricity network is unable to meet the forecast increase in demand over the coming years. To overcome this shortfall, we’re installing a new primary substation in the Bordon area.
Minimising travel disruption and noise are our priority
The nature of these work means that some sections of the upgrade will require a temporary traffic management system to be put into pace. These measures are being planned by SSEN in close collaboration with Highways England and local authorities, including East Hampshire District Council, with any customers in the affected vicinity being notified in advance.
We understand that these works may cause some disruption and noise, but we will follow industry best practices to ensure our contractors do everything they can to minimise any inconvenience. Look out for our maintenance signs across the road network for further information and diversions.
Details of the traffic management system will also be available on this page, together with any diversionary routes.
We have the environment in mind
The works are futureproofing and strengthening your area’s power supply to cope with severe weather events. It will also help support greater uptake of low carbon technologies.
We are committed to supporting the community by way of giving back to residents and communities that have faced disruption as a result of our works. We have supported two community events in Lindford and East Worldham during the period of the project. If you have an event or community project you would like us to support, we are always happy to consider ideas so please do reach out to our community relations team.
Find real time updates with our interactive map.
You can view our interactive map to provide real-time updates on the progress of our works. Each section of work is represented with a different colour and the pin shows the location of our team. You can click on each section of works for details of when the team will be in that location.
(Please accept our cookies in the bottom left to view our map):
You can also download our diversion route maps at the bottom of this page.
Priority Services Register
How to register for our Priority Services
Registering for our free Priority Services is easy. You can join our register by:
- Call us on 0800 294 3259 and register over the phone
- Clicking here and fill out our easy online form
- Or download the information booklet, fill out the application and send it to us by post by using our Freepost address
Contact us
We are a considerate constructor and want to help answer any questions you may have.
Have a query? You can email us at community@ssenbordon.co.uk or call us on 0800 046 9034.
Write to us using Freepost: SSEN BORDON.
Have a complaint? You can email us at customercomplaints@ssen.co.uk or call us on 0800 980 1395.
Write to us using Freepost: SSEN BORDON.
Concerned about vulnerability in a power cut? Visit www.ssen.co.uk/priorityservcies or call us on 0800 284 3259.
Discover more on our Smarter Electricity page.
Commonly asked questions
Download our resources
You can download our diversion routes, newsletters, and flyers so that you can share them in your community. As our project progresses we will provide you with the latest materials for you to download here.